Lacey, Washington

Official Website for the City of Lacey, Washington
  • Directory of Services | 
  • Contact Us
  • Small font
  • Medium font
  • Large font
  • Living in Lacey
  • Doing Business
  • Visiting Lacey
  • City Government
  • News & Events
  • City Council
  • City Departments
    • City Clerk
    • Finance
    • Human Resources
    • Police Department
    • City Attorney
    • City Manager
    • Community and Economic Development
    • Parks and Recreation
    • Public Affairs
    • Public Works
      • Public Works Home
      • Administration
      • Engineering Division
      • Operations and Maintenance
      • Water Resources
      • Solicitations
      • Forms and Applications
      • Plans and Documents
      • Project Updates and Alerts
      • Volunteer Opportunities
      • About Us
      • Frequent Questions
      • Contact Us
      • All City Departments
  • Homeless Response
  • Reports & Plans
  • Popular Forms
  • Lacey Municipal Code

 



Connect with us

Public Works

Print page

PROJECT UPDATES AND ALERTS

The latest information on roadway construction and other projects that could affect traffic, bus service, and/or daily routines. View projects on the interactive map below or scroll down for additional project information.

 

 

 

 

 



View larger interactive map



Hawks Prairie Sister Standpipe

Project Description

This contract provides for construction of a 2.0 MG potable water tank at 4040 Marvin Rd NE. The contract also includes frontage improvements on the east side of Marvin Rd NE, along the property. Construction is expected to being January 19, 2021, and take approximately one year to complete.


Carpenter Rd Utility Improvements and Overlay

Update 4/6/2021

The project is scheduled to begin on 4/12 and the utility work should be completed by the end of July and the Overlay contractor should start the beginning of August.

 

Project Description

This contract provides for the installation of approximately 3,000 LF of 6-inch, 8-inch and 12-inch diameter water main and 4,000 LF of 4-inch and 6-inch diameter sanitary sewer main along Carpenter Road SE between Stanfield Road SE and 37th Ave SE. Work to include service lines, meters, valves, transfer of water service, connections to existing water system, connections to existing sanitary sewer system, pavement restoration, lawn restoration and other work.

 

The City will hire a separate paving contractor in the summer to construct the overlay.

Ruddell Rd Retaining Wall

Update 4/6/21

The retaining wall and sidewalk are complete, contractor is working on electrical, lighting, fencing and lawn and landscape restoration.  Project expected to be complete in May.


Update 12/17/20


Tree removal has been completed. Construction on the new retaining wall is starting. Traffic will be reduced to one lane in each direction at times. Thank you for your patience.

   

Project Description:

This contract provides for construction on Ruddell Road from 27th Ave SE to Brentwood Drive for a precast        modular block retaining wall to include; minor widening with flatwork, stormwater, illumination, landscaping and        other work.

 

Construction will begin end of November 2020, and is expected to be completed by summer 2021.

 

FOR PROJECT UPDATES VIA EMAIL, PLEASE CLICK THE LINK AT THE TOP OF THE PAGE AND

SUBSCRIBE TO THE PROJECT NOTIFICATIONS


Hawks Prairie Road & Marvin Road Roundabout Improvements

Update 3/5/21

The roundabout will be closed Monday, March 8th to Tuesday, March 9th, from 7 a.m. to 9 p.m. Crews will install the final layer of asphalt. This work is weather dependent. There will be signed detours in place. Please note on the detour map below, yellow lines indicate closures to thru traffic.

 


       

Work is scheduled to begin on the Hawks Prairie Road & Marvin Road Roundabout Improvements project on Monday, September 28, 2020. Work will take place between 7am and 5pm, Monday - Saturday. 

The improvement project includes widening the current intersection from a single-lane to a multi-lane roundabout. Marvin Road frontage improvements, north of the intersection, are also part of this project. The project is expected to be complete in the spring of 2021.

       

During work hours, motorists can expect minor traffic disruptions. Alternate routes are advised. Please check back here for updates, or contact Tyson Poeckh, at tpoeckh@ci.lacey.wa.us or (360) 413-4384.

     

31st Avenue NE Closure

Update 1/20/21

A section of 31st Avenue NE will be closed to through traffic till the end of February for the construction of a gravity sewer line in 31st Avenue NE.

Capitol City Golf Club Estates Water and Sewer Improvements

Update 4/20/21

Please be advised that the intersection of Armour Dr SE and Yelm Highway will be closed to traffic beginning Monday 4/26 at 7:30 am and is expected to last throughout the day until the construction work is complete. The closure will include the portion of 58th Ave SE east of Armour DR. The work will include grinding asphalt, and utility construction including the installation of a sewer manhole, therefore traffic will be redirected to Ruddell Road to access the neighborhood through 65th Ave SE. If you live on 58th Ave SE and need vehicle access in and out of your home, please park your car in a location other than 58th Ave SE. If you have any questions or concerns, please contact Keven Inman at 360-239-0333 or Kinman@ci.lacey.wa.us. We apologize for the inconvenience, but thank you for your cooperation.
 

Update 4/6/21

The Capitol City Golf Course East Water & Wastewater Improvements project has reached the point where the contractor will begin paving another portion of the project where the water and wastewater infrastructure have been completed. This area is limited to Congressional Dr SE, 64th Ave SE, and a portion of Armour Dr SE. Please refer to the site map on the reverse side of this letter for the paving area highlighted in yellow.


Paving operations are currently scheduled for Thursday April 8, 2021, but is weather dependent.  If paving operations need to be postponed, they will begin at the next available paving window after the paving preparation has been completed. In the event that paving will be postponed, we will send out an e-mail notification as soon as we are made aware. When we have a new tentative date, we will send out another e-mail notification as well as update the City website and PCMS boards accordingly. 


During paving, we ask that any vehicles parked in the roadways be moved to an area that is not being paved. Access to these roads will be limited to local traffic only. Access to individual driveways will be restricted during the paving process until the asphalt is cool enough to drive over.


If you have any questions or concerns, please contact Keven Inman at (360) 239-0333. Thank you for your continued patience as we complete this project.



 

Update 3/23/21

Paving was completed along 65th Ave.  Another portion, 61st Ave, 63rd Ave and St Andrews Dr is scheduled for Friday, 3/26, weather dependent.

 

Update 3/22/21

Paving is scheduled for today, Monday, 3/22.

   

Update 3/16/21

The Capitol City Golf Course East Water & Wastewater Improvements project has reached the point where the contractor will begin paving another portion of the project where the water and wastewater infrastructure have been completed. This area is limited to 65th Ave SE from Ruddell Road to Congressional Dr. SE.


Update 2/9/21

The contractor is currently working on installing deep sewer main on Armour Dr and Armour Lp. There are crews also working on water and sewer connections, and landscaping restoration. Seed will be placed at a strategic time to allow the seed to grow. Paving will be placed based on suitable weather and temperature.  The contractor is anticipating that work will be complete in June for Phase I. 


Phase II of the project (the West portion of the neighborhood) will be advertised for bids this week, and we anticipate work will start in that area in May

Update 11/5/20

Due to current weather conditions, the paving date has been rescheduled to Monday, November 9th. Grading preparation of the roadway will continue November 6th.

Update 11/4/20

On Friday, November 6th, the contractor will be paving on 66th Ave, west of Ruddell Rd. Long delays are expected for anyone needing to travel through this area and alternate routes are advised. Residents on this street will have driveway closures as the paving is completed in front of each driveway, and lasting until the asphalt is cool enough to drive over. This work is weather dependent. Please call Keven Inman, the Project Inspector, at 360-239-0333 if you have any questions or concerns.


Update 9/15/20

Ruddell Road, St. Andrews St, 64th Ct and 64th Way are scheduled to be paved on September 21st -23rd. Work is expected to take place from 7am to 7pm, and please remember that vehicles cannot be parked on these roads during this work. Access to driveways may be limited for a couple of hours. The work is weather dependent, and any changes to the schedule will be posted here. For any questions, please contact City of Lacey Project Inspector Keven Inman at (360) 239-0333, or kinman@ci.lacey.wa.us. Thank you for your patience.

Update 5/6/20

The first phase of the project has been awarded to South Sound Contractors of Lacey, Washington. Construction is scheduled to begin on May 11, 2020, and anticipated to be completed in the summer of 2021.


Frequently Asked Questions



Due to changes in fire suppression standards over the years, the City of Lacey must replace the water lines in Capitol City Golf Club Estates with larger diameter lines. This will provide an adequate amount of water flow from the hydrants for firefighting. The City of Lacey is also designing a sewer line to serve the area. In 2006, the City observed nitrate concentrations increase in drinking water from Well #4 (located on West Sarazen SE). City staff believes the increase is primarily due to inadequately treated wastewater effluent from on-site septic systems.


This project will be completed in two phases over two years. Currently the first phase, which includes properties on the east side of CCGCE, has been sent out for bids. Bidding will open February 11th and a contract will be awarded on February 27th. We anticipate construction to start in spring of 2020. Please contact Linsey Fields at 360-486-8707 or lfields@ci.lacey.wa.us if you have any questions.


 Initial Contact Letter for CCGE Residents. 

 

Mullen Road Improvements

The City of Lacey and Thurston County are partners on the Mullen Road Improvements project to reconstruct a 0.9 mile section of Mullen Road SE from the Lacey City Limits to Carpenter Road. As part of this project, a roundabout is being proposed at the intersection of Mullen Road and Carpenter Road. The project is currently being designed and scheduled for construction in 2019. Thurston County is the lead agency on this project. For more information, please visit Thurston County's website.

  • Living in Lacey
  • Doing Business
  • Visiting Lacey
  • City Government
  • News & Events
  • Home
  • Sitemap
  • Get Adobe Reader
  • Privacy Policy
  • Contact Us
  • Login
Copyright City of Lacey, Washington, USA
Lacey, Washington